《环境工程学报》获“2017年度科学传播特殊贡献单位”荣誉称号    《环境工程学报》启用DOI通知设为首页|加入收藏
多元组合系统净化富营养化水体的示范工程
Demonstration project of eutrophic water purification by a multicomponent system
投稿时间:2017-09-15  修订日期:2018-02-28
DOI:
中文关键词:  富营养化  生态浮床  生态廊道  生物沸石  工程示范
英文关键词:eutrophication  ecological floating bed  ecological corridor  biological zeolite  engineering demonstration
基金项目:国家水体污染控制与治理科技重大专项(2013ZX07310-001)第一作者:贾锐珂(1992-),男,硕士研究生,研究方向:水污染控制。E-mail:563533462@qq.com*通信作者,E-mail:xcwang@xauat.edu.cn
作者单位E-mail
贾锐珂 西安建筑科技大学环境与市政工程学院 563533462@qq.com 
王晓昌 西安建筑科技大学环境与市政工程学院 xcwang@xauat.edu.cn 
宋佳 西安建筑科技大学环境与市政工程学院 515789086@qq.com 
摘要点击次数: 103
全文下载次数: 
中文摘要:
      杭州西湖上游龙泓涧受到周边茶园面源污染,水体出现严重的富营养化,为解决此问题,基于生物净化技术与工程措施相结合的思想,开展景观水体的净化处理示范工程研究。该工程根据河道特点,将生态廊道,生物沸石和生态浮床3 种技术组合,对水体进行多重净化作用,水质得到了明显的改善。多级生态廊道可相对延长水流的流程,尽量减少死水区和短流。生物沸石本身具有物理截留和吸附作用,表面形成的生物膜对富营养化水体中的污染物能保持长效和稳定的去除作用。以陶粒为载体,悬挂立体弹性填料的多层次立体生态浮床通过植物和微生物的共同作用对水体进行生态修复。结果表明,该工程净化效果良好,对水体中的COD、TP、TN、NH4+-N、NO3--N 的平均去除率分别为24%、46.24%、31%、24.43%、13.42%,达到示范工程的预期目标,并且夏季的处理效果高于冬季,该技术具有一定的应用前景。
英文摘要:
      Non-point source pollution from tea plantations in the upstream of West Lake caused severeeutrophication in the Longhong stream. Therefore, an in-stream treatment system combining biological purification technologies and engineering measures was devised to treat the water and to serve as a demonstration project for the purification of eutrophic landscape water bodies. Considering the characteristics of the stream channel, a treatment system combining an ecological corridor, bio-zeolite, and ecological floating beds, was used, which significantly improved the water quality. On the one hand, the multi-stage ecological corridor prolonged the flow path and prevented the formation of dead water zones and hydraulic short-circuiting. On the other hand, the bio-zeolite showed a physical interception effect, which also maintained long-term and stable removal of pollutants from the eutrophic waters by the biofilm formed on its surface. Moreover, the multi-layered three-dimensional ecological floating bed, which served as the carrier of ceramic particles and suspended elastic packing, ensured ecological restoration of the water body through the joint action of plants and microorganisms. Overall, the demonstration project exhibited good pollutants removal efficiencies of COD of 24%, TP of 46%, TN of 31%, NH4 +-N of 24%, and NO3 --N of 31%. Furthermore, a higher treatment efficiency was achieved in the summer than the winter. So, the project has a good application prospect.